POSEYVILLE, IN (JULY 22, 2021) – We are expanding our Custom Fabrication Shop on Frontage Rd., north of Poseyville to add greater crane capacity, taller headroom, and more production space. Our Pre-Production Team (estimating & engineering) will also be relocating to Frontage Road. This will provide them with better office space and also be closer to the work they are supporting.
As of now, Arc Construction (the general contractor) has broken ground on the high bay. The pad is complete along with the laydown yard extension. The next step will be to start digging footings for the building columns and pour the concrete pad. The pre-engineered building package should drop by the third week of July and hopefully, we are erecting steel in August. We are still shooting for substantial completion of this project by the second week of October.