POSEYVILLE, IN (September 30, 2021) – As of now, the highbay project is moving forward and on schedule. Since last quarter we have really seen good headway. The building pad, concrete, and steel erection are all complete. The building is currently in the process of being sheeted and should be completed by the second week in October.
Up next will be mechanical/electrical, fire suppression system, and tieing the two buildings together (removing south wall of existing building to merge the two buildings). Our Structural Fabrication team members are currently in the process of fabricating the 25 ton crane runway and bridge beams. The crane system will be erected in house and shooting to be operational by the end of the year.
Site work should be wrapped up by the end of October.